Wednesday, July 18, 2007

Well, well, well.


July 17, 2007 : The well has been drilled and preliminary reports from Hillard Walls put it at 140' deep at 12 gallons a minute. That's flow. Just hoping for no iron or radon now.

The tailings are distinctly pink from the local granite.

Saturday, July 14, 2007

Sure footing...


Joel at work

Looking west


Light areas are exposed ledge


75% done by 10am


Resuming work on the longhouse after a week's hiatus, the foundation crew of two quickly formed the footings for our house. We coordinated the final top of foundation height on site to ensure the house wouldn't rise too far above the surrounding grade, we'll know soon enough if our calculations yielded the intended result.

We're told that the footings will be stripped tomorrow and they'll being forming the walls on Monday (July 16th) for a pour sometime next week.

Another unexpected issue arose while on site regarding the power drop from Bangor Hydro. The nearest utility pole sits about 10' beyond our property line. We're obviously not able to run buried service from that pole to our house as we don't own the property. All of this means we need to contact a line company, set a new utility pole on our property which we'll run primary power to, set the meter and continue on to the house with our buried service. Amazing what a straight creosote impregnated limbless tree goes for these days...$1000. It doesn't stop there, if they hit ledge you pay an additional anchorage fee plus guy wires for anchorage. Then the power company adds their $250 fee to 'drop' service to you on the pole that you provide. This will draw down the contingency fund but it's a great case for having one in the first place.

We're quite pleased that the groundwork is progressing and eagerly anticipate the wall pour this week.

Sig, 'throwing metal'


If only they left the keys...

Thursday, July 5, 2007

Excavation begins

Looking East - Master Bedroom in foreground

Excavation for the main volume of the house began on Tuesday and our fears of hitting ledge have been realized. The far upper right corner shows 6' from existing grade to the bottom of the hole (where we hit ledge). That will be taken up by gravel, 1' of footing and only about 5' of wall. The ledge dives down a bit in the center of the house but rises again near the dining room and living area.
Lacking the funds to blast we'll be working with what's at hand, pinning the footings to the ledge and pouring a 2" covering slab over the exposed ledge. We're counting on substantial storage area in the basement so we may raise the building out of the ground a bit more than we had planned. It's important that we maintain 4' of cover on the footings to avoid heaving issues so more fill around the house may counter the raised elevation of the foundation wall.
Hopefully today the last of the digging will take place and we'll have a better idea exactly what elevations we'll be dealing with. It's not the deep full height basement we were planning on but we're hopefully we can squeeze 6' clear beneath the floor framing.
The weather has been great and allowed the foundation contractor to get caught up and we're hopeful the forms will arrive on site soon.
Looking East - Bedrooms at far end

Center of house looking South - more elevation to work with...


Wednesday, June 27, 2007

Field in the forest

Field

Insert Tank Here

Wednesday June 27th

The septic field has been installed which consists of 10 concrete end-fed chambers and today the concrete holding tank will be set. We've encountered ledge in many spots but have enough cover to make the tank work. We’ll have to shift the foundation slightly to the west to miss a stubborn knob of granite near the boys’ bedrooms but we’re hopeful that will be the only ledge under the building.

I’ll be setting the height for the top of foundation wall this weekend in preparation for the concrete form-work arriving next week. We’re doing our best to marry the building with the site grading, but given the overall length of 80' it’s a challenge. We have about 38” of natural drop-off from one end of the building to the other and need to swale the water around the house to maintain proper drainage. Ideally, we would be dropping the east end of the building (the boys’ bedrooms) by a couple of feet to keep the west end from becoming a ship’s prow sticking out of the earth. Foundation contractors love dropping 8’ foundations in 4’ holes, which makes their work easier but means a lot more fill to hide the walls. It also means steps to get into the house. We’re trying to preserve the house’s connection to the land by closely tying the existing grades to the imposed order of the house and minimize the amount of fill required.

Next week, foundation. Perhaps.

Friday, June 22, 2007

Fill...in the void

Driveway Entrance
Approaching the house site

Septic field ahead, Sig to left


Laying out the septic field


After signing our contract last Saturday morning, June 16th, I arrived on Tuesday evening to stack some logs to find the silt fence placed at the perimter of the building site. A phone call from our builder Wednesday morning asking for the building permit assured us they were ready to begin work.

Thursday they roughed in the driveway, grubbed out (removed the stumps) the foundation site and began prepping the septic field. The boys and I made a trip over Friday morning to watch the excavator and met Bruce and 'Duke'. I was politely told that my rather large brush piles would be in the way when they started excavating for the foundation. Coincidentally (wink-wink), Duke owns a chipper and has just enough time in his schedule on Sunday to chip up the piles. After researching how much a chipper rental would cost ($250 + fuel + my time), I decided a not-to-exceed price of $500 to chip everything was a worthy investment. His offer to trade for firewood was less than generous so I decided to keep it for our own use.


Fun with dirt


Henning ran into the forest saying, "He's coming up here, he's coming up here!" when the excavator started up, Sig just kept eating gravel.

Thursday, June 7, 2007

Permit, check.



Three permits actually, building permit, driveway opening permit, and the subsurface wastewater disposal permit (septic system). There are others of course, but no more that we need to coordinate. The plumber will pull his permit when he begins work inside, no electrical permits as is typical in most locales, though the CEO (code enforcement officer) checks for basic National Electrical Code compliance. We're happy to have crossed this hurdle, having checked with the CEO prior to purchasing the land to be sure we could place the house where we wanted to place it, we assumed it was merely a formality but there was an outside chance that something was missed during the intial evaluation.

Had we chosen to let our contractor pull the building permit for us we would've spent an extra $420. The process is straightforward, if you can handle registering your car, you shouldn't have any trouble pulling a building permit, you certainly don't need any special drawing skills, napkins are even acceptable.

Step 1: Any designed septic system will be accompanied by the necessary three copies for CEO approval and will have complete information that the State of Maine requires. You'll pay between $300-400 for the septic design but this is money well spent as the requirements for this permit are specific and tedious. You'll receive the design in triplicate ready for your signature and submission.

Step 2: Building permit application. Find your tax map and lot number, the CEO can then tell you the zoning district you reside in. Each zone has different requirements for setbacks make sure you comply with every single one of these standards. Small lots are usually more problematic in this regard.

Step 3: Driveway opening permit. Fill out the form...no fee, and they have to grant you at least one entrance permit. They'll check the road width and length and be sure you're in compliance with their standards. If your driveway is long beware, you may have to build a much wider road to allow fire vehicles passing space. Sitework is a significant expense so making a road wider by just a few feet will cost a lot of money.

If you have wetlands on your property, be sure to consult with the DEP and your local CEO. The more information you have and they have the smoother the process will go...and get absolutely everything in writing you'll need it. We had no trouble communicating wetland information to the CEO after meeting with the DEP and getting a letter from them stating the outcome of that meeting.

Our next step...sign the contract with our builder and wait for the trucks to arrive.

Monday, June 4, 2007

Blue skies

Ready for the earthwork to begin

Thanks to many hours of hard work from our friends and three weekends worth of work, we've managed to carve out enough room in the forest to place our house. Until our builder arrives and tells us that we haven't left nearly enough room for their equipment to manuever. Our thanks to Uncle John, Patrick, Gareth & Fengyun for your hours in the forest helping us get the project off and running.


Felling trees without the aid of a chainsaw is considerable work.


After one trip to the hardware store to purchase a wedge, hand axe and a handsaw and one-half hour of hand-cutting, this tree succumbed to gravity.



This doesn't need a caption.